an incinerator for food waste and polythene waste management

an incinerator for food waste and polythene waste management. as per our requirements we would like the YD 15C small incinerator.Mixed Biomedical waste Incinerator.Contract period:To be decided by the supplier
Payment terms:100% prepayment through bank TT after signing of contract.

Please confirm your willingness to execute this contract project by sending brochure and your price quotation for the below specification to enable us submit it to the firm incharge of the contract for their study and approval.

Type of Waste: Mixed Biomedical waste.THE INCINERATOR AS REQUESTED BY OUR CLIENT SHALL BE SEMI AUTOMATIC WITH:
WASTE BUCKET/TANK – ABOUT 2000KG
CAPACITY OF FEEDING: ABOUT 600-800Kg AT A TIME.
BURNING AT ABOUT 150/165-200 IN 60MINS
THE BURNER SHALL USE DIESEL/OIL
WITH CHIMNEY, ELECTRIC PANNELS,ELECTRIC MOTORS,ETC.
MATERIALS FOR DISPOSAL: SHARP MEDICAL WASTES.

1. Waste burning capacity of unit: 100-125 kgs / hr.
2. Mode of waste handling : Autoloading– DFDV + Bucket elevator
3. Type of fuel : LDO / HSD
4. Type of Burner operation : Automatic
5. Expected fuel consumption: 30-35 kgs/hr **(depending upon overall
mix of the waste, moisture
content, etc.) after preheat.
6. Connected electrical load : Approx. 7-8 KW (AC 3 phase,220V, 50 Hz).
7. Overall space requirement : 9 m (L) X 8 m (W) X 6 m (H) Each unit
without stack

Burners temperature controlled (TIC – Thermocouple) and work on ON –
OFF basis. The frequency on ON – OFF will depend upon the nature of
waste, moisture content, calorific value, etc. and shall vary from waste to
waste. The fuel consumption also depends upon the frequency of the door
opening and method of operation of the incinerator. We have mentioned
approx. expected fuel consumption figures.

The Incineration System comprises of :

I. Main Incinerator with
A. Primary & Secondary Chamber Modules duly refractory lined, piped & wired.
B. Bucket elevator + DFDV mechanism for autoloading and Deashing
mechanism
II i. 1 No. fully automatic Fuel Oil burner for primary chamber.
ii. 1 No. fully automatic Fuel Oil burner for secondary chamber.
III. Centrifugal forced draft fan assembly complete with motor drive, duct and
dampers, etc. mounted on the common skid of the unit to provide :
Combustion air.

Eductor air.
IV. Eductor Assembly for :
Cooling of exhaust gases from 900 – 1000 0 C to around 350 0 C .
Keeping the entire system under negative pressure to avoid hot gases / dust
particles rushing out of charging door.
V. Electrical Control Panel along with safeties, and Audio / Visual
indicators and
/ or alarms for efficient and safe operation of the system.
VI. Electrical wiring of the unit.
VII. Oil tank of 1000 ltrs capacity mounted on the skid
VIII. Operating tools and tackles comprising of – rake, hoe, shovel (I No. each).
IX. Chimney of  2.5 Mtr height.