hog insinerators

End

All equipment shall be painted with a coat of zinc rich primer and 2 coats of high temperature resistant resistant

polyurethane type paint. All painted surfaces shall be ready by steel shot cleaning or sand blasting.

 

Identification and Name Plates

name and Identification plates comprising the manufacturer’s name, model number, serial number, along with other relevant

information will be securely fastened to the device in easily visible locations.

 

Gas Type and Tank

All burners will be gas oil (diesel) fired. For many incinerations fitted with fuel oil (petrol ) form juicers, the

bidder will supply and install 1000 litres steel tank along with all the essential valves and valves and first supply of

1000 litres gasoline oil. Where existing gasoline is found to be still in good shape from site review, contractors must

utilize existing tanks and consequently must clearly define in their own bids of this use. The tank shall be put in

least two meters above floor on steel frame next to the incineration shed. Gas delivery to incineration burners shall be

by gravity feed. The tank should be fitted with a drain plug as standard.

  1. Post – combustion chamber:

Basic requirements:

1-Capacity 100kg/hr.

2-Work for 24 hours.

3-Unit must have enough combustion room consists of two combustion chambers (mounted vertically)

4- Unit must supply with control methods for air entry to the primary and secondary chambers and therefore incineration

of the waste is achieved.

5-The device charging is done mechanically and also have an option to be done manually.

6-The ash removal is done mechanically and have an alternative to be done manually

7-The device needs to have a dry filtering device.

8-The device should be controlled from the control panel.

control panel:

Should show different tasks of operation utilizing (PLC)

-Temperature in combustion room

-time of combustion and operation.

-different pressures.

-amount of air in combustion.

-efficiency indicator.

-emergency system in case of increasing temperature or pressure.

f- Time for gasoline death:

Minimum time required for passing to combustion room for oxidizing 0.5 minutes at 800 degree Celsius.

1- style details:

A-primary combustion room:

Oxidize all waste to combustion residuals and temperature less than 800 degree Celsius.

b- Secondary room:

Continue combusting combustion gasoline residuals and hanging particles utilizing additional burner temperature less than

1100 degree Celsius and this situation is attained by harmonizing between temperature and time of passing to guarantee

adequate oxidizing supplying enough air to guarantee turbulence of gasoline all the time this is controlled from control panel.

Continue combusting combustion gas residuals and hanging particles using additional burner temperature not less than

1100 degree Celsius and this conditions is reached by harmonizing between temperature and time of passage to ensure

adequate oxidizing supplying enough air to ensure turbulence of gas all the time this is controlled from control panel.

Categories: