The successful Bidder shall notify CEB in writing at least three (3) weeks prior to the carrying out of mill tests
in order to enable sending of a CEB Engineer for witnessing of the mill tests. A’Factory Acceptance Test
‘ schedule will likely be
mutually agreed between the successful Bidder and the CEB Engineer.
NOTE: All charges inclusive of air tickets, meals & hotel accommodation, local transportation and other living expenses
for your CEB Engineer shall be borne by the successful Bidder.
The successful Bidder shall submit to the CEB Engineer the following documents Before shipment of the incineration
Collection. Certification of Conformity inclusive of the clause’We certify that, subject to concessions or exceptions
listed here after, the provides detailed above were fabricated in accordance with the technical specifications of their
contract, order and therefore, all tests and inspections having been finished, the provides comply in every aspect using the
applicable particular specifications, drawings, and applicable standards and regulations in force’.
? Factory Acceptance Test(FAT) Certificates
? Bill of Material (BOM)
? Three(3) Complete Sets of As-Built Drawings
? Installation and commissioning process of the incineration set.
? Program of functions for carrying the setup and commissioning
? Labour and logistic requirement for carrying the installation and commissioning.
? All electric drawings and wiring diagrams
Form of Waste: To take care of medical waste, categories A, B, C, D,E
Sort of incineration: Pyrolytic
Nominal Burn Speed: 50 to 60 Kg/hrat 3500Kcal/Kg
Loading: Manual, Batch Load
De ashing: Automatic or manual batch de ashing
The incineration must avoid the release of black smoke and
fine dust, during the loadings
Primary Chamber Capacity: 2 -3 m3
The insulation of the combustion chamber should be composed of
refractory bricks, having a high content of aluminium and insulates,
The plate of combustion in carborundum avoiding the mending of
glass and slags
Hours of operation/day: 10 hrs
Max operating Temperature: 14000C
Normal Operating Temperature (Main ): 8500C
Operating Temperature (Secondary): 11000C
It should have temperature regulators in digital watch:
Carbon Content of Ash: <2%
The setup should be completely free from visible smoke as well
as offensive odours.
Residence Time in Second Chamber: two seconds minimum
The Inner diameter of the Chimney: Ø 400
Height of Stack: 8 m
Burner performance: Automatic On/Off
Fuel: Diesel
Fuel Consumption at rated capacity: 7 Kg waste/ltr
Electricity Consumption: <2kW at rated capacity
Operating Voltage: 220-240VAC 50 Hz
Spare Parts: Provide for 1 year lent as alternative
Consumables: Provide for a single year of performance to be mentioned
as alternative
Guarantee: Parts and service support: 1 year minimum article
commissioning
Service Support: Swing 72 hours.
Emission Standards Compliance: BS 3316 or équivalent standard
Process Filtering method: Scruber to be mentionned as alternative
CE Manufacturing Compliance: BS EN 746-2-1997
Design Specification: Types A, B, C, D, and E of Health waste
Installation and Commissioning: Included in conditions of supply
Coaching in preventative and therapeutic maintainance and use
of their incineration: Operator training inclusive in provide
Capability to cure Plastic: Not less than 40 percent by weight
Decrease of their incineration
Shelter of the incineration inclusive in offer (the protector must possess
facilities for hand washing and firefighting).
This material and equipment must include in the shed of the
incineration:
* Foundation in rubble stone,
* Isolation roof against humidity;
* Elevation with brick of 20 cm (bloc cement), ongoing lintel
(linteau) in reinforced concrete;
* Steel frame (charpente en steel );
* roof in sheet B.C.A. 28 BG (Toiture en tôle),metal gutter,
* Sanitary installation (wash basin, soak way pit of 20 m of depth);
* Ash pit of 30 m3,
* Electrical setup;
* Concreteslab for mending the incineration;
* Chanel for evacuation of rain water or waste water
* Wiremesh for aeration up the lintel;
* smoothrougtcasting of walls (interior and outdoors );
* plinth with cement;
* two metal doors;
* Enemail paintings indoors and latex paintings outside the shield
on walls and on walls;
* roof limit (planche de rive);
* Measures with this specification will be contingent on the size of the
incineration which will decide on the size of the shed of the incineration.
* Roofing limit (planche de rive);
* Measures for this specification will depend on the size of the
incineration which will determine the size of the shed of the incineration.