  1. Ensure flame contact with all gases is achieved. –yes
  2. Ensure residence time is not less than two (2) seconds. –yes
  3. Ensure the gas temperature as measured against the inside wall in the secondary chamber & not in the flame

zone, is not less than 1100oC. –1000-1200 oC

 

  1. Ensure the oxygen content of the emitted gases is not less than 11%.–yes
  2. Ensure both primary and the combustion temperatures are maintained until all waste has been completely

combusted–yes

 

5     Particulate Removers An mechanical particulate collector has to be integrated after secondary combustion

room for removal of particulate pollutants entrained in the flue gas flow. The chimney should have a minimum height of 10 meters above floor level and clear the

best point of the building by not less than 3 meters for many roofs. The topography and elevation of adjoining buildings

within 50 meters radius ought to be taken into consideration. –6 meter can and 4 meters, free price

 

unacceptable.

 

wind speed x 2) whichever is greater to guarantee no down washing of leaving gases. . –yes

 

 

 

  1. If possible the chimney should be visible to the operator from the feeding area.—according to local site
  2. The addition of dilution air after combustion in order to achieve the requirement of these guidelines is

 

7     Instrumentation   Instrument for determining the inside wall temperature rather than burner flame temperature has to be

  1. The minimum exit velocity should be 10 m/s and at least twice the surrounding wind speed (Efflux velocity =

supplied for both primary and secondary chambers. –yes

 

under the required temperature.

  1. Point for the measurement of emissions shall be provided. .–yes

Capacity       less than 500Kg/hr.

Operation     24hr-7days/week continuous operation.

Combustion room 2 combustion chamber.

Temp.    First combustion room 800-1000 C.

Secandry combustion room 1000-1200 C, with the Option to be updated to 1400

  1. An audible and visible alarm must be installed to warn the operator when the secondary temperature drops to

below the required temperature.

Capacity       Not less than 500Kg/hr.

Operation     24hr-7days/week continuous operation.

Combustion chamber 2 combustion chamber.

Temp.    First combustion chamber 800-1000 C.

Secandry combustion chamber 1000-1200 C, with the possibility to be upgraded to 1400